• Skip to primary navigation
  • Skip to main content
  • Skip to footer

News and entertainment worth sharing – York and North Yorkshire

  • News
  • Things to do
  • Radio
  • Vouchers
  • Categories
    • Business
  • More
    • Comments
    • Advertise
    • Contact us
City Cruises York

Closed for a YEAR: When will flood-hit main road in North Yorkshire reopen again?

The A19 during the 2021 Floods - Photo from Mark Sayer
Tuesday 16 February, 2021 @ 6.57 am News David Dunning
Share via...

Action is being taken to keep reconstruction of the A19 at Chapel Haddlesey, south of Selby, on course after the project was halted temporarily last month by the impact of Storm Christoph.

It’s been closed for a year now.

Once again in 2021 floodwater overtopped sections of the road following persistent heavy rain, but North Yorkshire County Council’s contractor was back on site to resume work at the beginning of February.

The main photo shows parts of the road under flood water again earlier this year.

Repair work is going on but it’s been a year since it first closed
All pictures from North Yorkshire County Council

North Yorkshire County Council’s highways team and contractor Balfour Beatty have worked together to ensure work could get underway again as soon as it was safe.

The target remains to reopen the road in June this year.

Following Storm Christoph, the highways team and contractor are introducing measures to keep the project on course and potentially save time.

One of these is creating off-site stockpiles. These will mitigate any delay in the supply of materials from quarries and allow two sections of the works to be undertaken simultaneously.

Revised schedule

The contractor has revised their schedule to allow works that are clear of floodwater to be done earlier than originally planned.

A review of the work needed to culverts means work can begin on rebuilding their stone parapet walls, reusing some existing material, supplemented by new stone.

With the first section of the reconstruction of the embankment and road structure heading towards completion, construction machinery to lay the new road surface is due on site on Monday, 8 March, for the initial road surfacing work.  

County Councillor Don Mackenzie, executive member for access, said: “We understand the frustration of local people and their desire to see this work completed and the road reopened as soon as possible.

“On 18 February, we mark one year since the road closed and we do not underestimate the inconvenience to people locally during that time. Many of our own staff not only work in the area, but live there, too, so they experience the disruption first hand.

“When the road collapsed, our highways team faced a major task.

“Planning, design, procurement and mobilisation for a project of this size would normally take more than a year in itself, but we swiftly completed this process as well as setting aside the funds so that we were able to award the contract and begin the process of repairing the highway.

“We have made significant progress and our teams are doing all they can to reopen the road as soon as possible.”

‘Did its job’

Cllr Mackenzie said that despite floodwater overtopping sections of the road during Storm Christoph, the reconstructed sections worked well.

“Where the new rock armour construction on the embankment is in place, it did its job, standing up well to the flood and remaining intact,” he said.

“Sections of the old road still to be reconstructed did flood, but when complete these will have a new embankment with a stepped construction with rock armour in place for future protection and resilience. None of the new construction has yet reached its final road height.”

Nigel Adams, MP for Selby and Ainsty, said: “The rebuilding of the A19 is a top priority for everybody in Selby district, and I will continue to monitor progress very closely.

“It is reassuring that the newly completed section of the new causeway has not been damaged by this month’s flooding, and this bodes well for the final scheme.

“The winter months were always going to be a challenge, and it is imperative that all possible steps are taken to complete the rebuild as soon as possible.”

The county council says the reconstructed A19 has to remain within its existing footprint. Raising it further would have meant taking additional land, acquisition and planning requirements leading to further delays and considerably increased costs. The scheme will provide a significantly more resilient road than was the case previously.

Storm Dennis 2020

The A19 between Chapel Haddlesey and Wand Lane, Eggborough, closed one year ago, on 18 February 2020, when the River Aire broke its banks during Storm Dennis.

The A19 at this point is on a causeway. It is built up because it crosses a flood plain. Strong winds during Storm Dennis caused water in the flood plain to lap across the top of the road and against the side of the carriageway. This eroded the embankment in several locations, causing some of the carriageway to subside and crack.

Despite the size of the challenge and ongoing adverse weather, the County Council highways team inspected the site as quickly as possible and engaged a highway design consultant to produce a design that would allow the contractor to begin reconstruction.

The most significant issue was that the scale of the damage was unknown. The investigation and design process were delayed by very slow dissipation of water, the availability of specialist equipment and the Covid-19 pandemic.

In June, it became clear that major diversion works were required to ensure the long-term integrity of important BT and gas services utilities located near the road and embankment. This required utility companies, including Northern Gas Networks and BT, to divert and replace their equipment.

Contractor Balfour Beatty began reconstruction in October. Since then, extensive progress has been made in excavating the old road surface and causeway as well as installing rock armour, which will provide protection against future flood damage to the overall structure of the road.

Footer

YorkMix
News 01904 848 766
Email YorkMix news »
5-6 King's Court, Shambles, York  YO1 7LD
YorkMix Radio
General enquiries 01904 375 029
Studio/competitions 01904 375 030
Email YorkMix Radio »
Selby Superbowl, Bawtry Road, Selby  YO8 8NA
YorkMix is a trading name of YorkMix Media Ltd
Registered in England
Company number: 07814727
VAT number: 154 0364 34
© York Sound Ltd

Copyright © 2022 YorkMix Media Ltd

We use cookies on our website to give you the most relevant experience by remembering your preferences and repeat visits. By clicking “Accept”, you consent to the use of ALL the cookies.
Cookie settingsACCEPT
Manage consent

Privacy Overview

This website uses cookies to improve your experience while you navigate through the website. Out of these, the cookies that are categorized as necessary are stored on your browser as they are essential for the working of basic functionalities of the website. We also use third-party cookies that help us analyze and understand how you use this website. These cookies will be stored in your browser only with your consent. You also have the option to opt-out of these cookies. But opting out of some of these cookies may affect your browsing experience.
Necessary
Always Enabled
Necessary cookies are absolutely essential for the website to function properly. This category only includes cookies that ensures basic functionalities and security features of the website. These cookies do not store any personal information.
Non-necessary
Any cookies that may not be particularly necessary for the website to function and is used specifically to collect user personal data via analytics, ads, other embedded contents are termed as non-necessary cookies. It is mandatory to procure user consent prior to running these cookies on your website.
SAVE & ACCEPT